Service timetable
20:59 Dalmuir to Bathgate Lmd
Tuesday 6 October 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 75 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Dalmuir | 1 | 20:59 | 21:00 | +1 min | ||
| Dalmuir Down Siding | 21:01 | 21:20 | 21:02 | 21:21 | +1 min | |
| Dalmuir | 4 | 21:22 | 21:26 | 21:21 | 21:22 | -4 min |
| Yoker | 21:29 | 21:30 | 21:25 | 21:25 | -5 min | |
| Garscadden | 1 | 21:34 | 21:36 | 21:29 | 21:29 | -7 min |
| Glasgow Queen Street Low Level | 9 | 21:44½ | 21:46½ | 21:39 | 21:39 | -7 min |
| Airdrie | 3 | 22:03 | 22:05 | 21:55 | 21:55 | -10 min |
| Bathgate | 1 | 22:18 | 22:20 | 22:16 | 22:18 | -2 min |
| Bathgate Lmd | 22:22 | 22:20 | -2 min | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.