Detailed timetable
08:17 London Fenchurch Street to East Ham E.m.u.d.
Wednesday 7 October 2026
Planned service information
- Power type
- Electric multiple unit
- Timing load / planned train type
- 357
- Maximum speed
- 100 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| London Fenchurch Street | 4 | 08:17 | 08:23 | +6 min | ||
| Christian Street Junction | pass | 08:19 | 08:25 | +6 min | ||
| Gas Factory Junction | pass | 08:22½ | 08:30 | +8 min | ||
| West Ham | pass | 08:26 | 08:33 | +7 min | ||
| East Ham E.m.u.d. | 08:31 | 08:38 | +7 min | |||