05:41 Canada Water to Battersea Park
Wednesday 7 October 2026
Planned service information
- Power type
- Electric multiple unit
- Timing load / planned train type
- 378
- Maximum speed
- 75 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Canada Water | 3 | 05:41 | 05:42 | +1 min | ||
| Surrey Quays Silwood Junction | pass | 05:42½ | 05:43½ | |||
| Old Kent Road Junction | pass | 05:49 | 05:45 | -4 min | ||
| Peckham Rye | 1 | pass | 05:58 | 05:47 | -11 min | |
| Crofton Road Junction | pass | 05:59 | 05:48 | -11 min | ||
| Denmark Hill | 1 | pass | 06:01 | 05:49 | -12 min | |
| Voltaire Road Junction | pass | 06:05 | 05:53 | -12 min | ||
| Factory Junction | pass | 06:05½ | 05:53½ | |||
| Battersea Park | 2 | 06:08 | 05:56 | -12 min | ||