Service timetable
17:54 Upminster L.t. to Upminster L.t.
Wednesday 7 October 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 45 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Upminster L.t. | 17:54 | |||||
| Turnham Green Lt | 19:11 | 19:11 | ||||
| Gunnersbury | 1 | 19:14 | 19:14 | 19:18 | 19:18 | +4 min |
| Kew Gardens | 2 | 19:17 | 19:17 | 19:21 | 19:21 | +4 min |
| Richmond Nll | 7 | 19:22 | 19:35 | 19:25 | 19:35 | On time |
| Kew Gardens | 1 | 19:39 | 19:39 | 19:39 | 19:39 | On time |
| Gunnersbury | 2 | 19:42 | 19:42 | 19:42 | 19:43 | +1 min |
| Turnham Green Lt | 19:45 | 19:45 | 19:45½ | 19:46 | +1 min | |
| Upminster L.t. | 20:59 | 21:00 | ||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.