Detailed timetable
00:04 Sheffield to Etches Park Sidings
Thursday 8 October 2026
Planned service information
- Power type
- Diesel multiple unit
- Timing load / planned train type
- 810
- Maximum speed
- 125 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Sheffield | 1 | 00:04 | 00:07 | +3 min | ||
| Nunnery Main Line Junction | pass | 00:05½ | 00:08 | +3 min | ||
| Woodburn Junction | pass | 00:11½ | 00:10 | -1 min | ||
| Woodhouse Junction | pass | 00:20 | 00:15 | -5 min | ||
| Beighton Junction | pass | 00:22½ | 00:18 | -4 min | ||
| Barrow Hill North Junction | pass | 00:30 | 00:24 | -6 min | ||
| Tapton Junction | pass | 00:33 | 00:27 | |||
| Chesterfield | UBH | pass | 00:33½ | 00:27 | -6 min | |
| Chesterfield South Junction | pass | 00:34½ | 00:28 | -6 min | ||
| Clay Cross North Junction | pass | 00:37 | 00:30 | -7 min | ||
| Ambergate Junction | pass | 00:43½ | 00:38 | -5 min | ||
| St.mary's South Junction | pass | 00:51½ | 00:43 | -8 min | ||
| Derby | 00:54 | 00:55 | 00:46 | 00:46 | -9 min | |
| Etches Park Sidings | 00:58 | 00:47 | -11 min | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.