Detailed timetable
12:42 Hanwell Bridge Loop to Harlow Mill Fhh
Thursday 8 October 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 2000
- Maximum speed
- 60 mph
- Operating characteristics
- Q
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Hanwell Bridge Loop | UGL | 12:42 | ||||
| Hanwell | 3 | pass | 12:43 | |||
| West Ealing | 4 | pass | 12:45 | |||
| Acton West | pass | 12:47½ | ||||
| Acton Main Line | UGL | 12:53 | 12:56 | |||
| Acton Wells Junction | pass | 12:59 | ||||
| Willesden Junction High Level | 4 | pass | 13:01 | |||
| Kensal Green Junction | pass | 13:02 | ||||
| West Hampstead | 2 | pass | 13:09½ | |||
| Gospel Oak | 2 | pass | 13:15½ | |||
| Camden Road Junction | pass | 13:21½ | ||||
| Camden Rd. E. Junction | pass | 13:23½ | ||||
| Westbourne Road Junction | pass | 13:27 | ||||
| Canonbury West Junction | pass | 13:29 | ||||
| Navarino Road Junction | pass | 13:33½ | ||||
| Lea Junction | pass | 13:40 | ||||
| High Meads Junction | pass | 13:41 | ||||
| Temple Mills East Junction | 13:44 | 14:32 | ||||
| Coppermill Junction | pass | 14:39½ | ||||
| Tottenham South Junction | pass | 14:40½ | ||||
| Brimsdown | pass | 14:48½ | ||||
| Cheshunt | 2 | pass | 14:52½ | |||
| Broxbourne | 4 | pass | 14:58 | |||
| Broxbourne Down Pass Loop | 15:00 | 15:03 | ||||
| Broxbourne Junction | pass | 15:06 | ||||
| Harlow Town | 3 | pass | 15:11 | |||
| Harlow Mill | 15:14 | 15:15 | ||||
| Harlow Mill Recp. | 15:19 | 15:21 | ||||
| Harlow Mill Fhh | 15:23 | |||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.