Detailed timetable
21:37 Woking to Northam C.s.d.
Thursday 8 October 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 100 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Woking | 6 | 21:37 | 21:35 | -2 min | ||
| Woking Junction | pass | 21:38 | 21:36 | -2 min | ||
| Guildford | 4 | 21:47 | 21:49 | 21:44 | 21:44 | -5 min |
| Shalford Junction | pass | 21:51 | 21:46 | -5 min | ||
| Farncombe | pass | 21:53 | 21:48 | -5 min | ||
| Haslemere | 1 | 22:03½ | 22:05 | 22:00 | 22:00 | -5 min |
| Petersfield | 2 | pass | 22:16½ | 22:16 | On time | |
| Havant | 2 | 22:34½ | 22:36 | 22:32 | 22:32 | -4 min |
| Farlington Junction | pass | 22:40½ | 22:38 | -2 min | ||
| Cosham Junction | pass | 22:41 | 22:39 | -2 min | ||
| Cosham | pass | 22:42 | 22:40 | -2 min | ||
| Fareham | 1 | 22:48½ | 22:49 | 22:49 | 22:49 | On time |
| Swanwick | pass | 22:53½ | 22:56 | +3 min | ||
| Hamble | pass | 22:57½ | 23:00 | +3 min | ||
| Sholing | pass | 23:00½ | 23:04 | +4 min | ||
| St Denys | pass | 23:05½ | 23:09 | +4 min | ||
| Northam Junction | pass | 23:11½ | 23:12 | +1 min | ||
| Southampton Central | 3 | 23:14½ | 23:23 | 23:15 | 23:25 | +2 min |
| Northam Junction | pass | 23:25½ | 23:29 | +4 min | ||
| Northam Depot Recept Line | 23:27 | 23:34 | 23:31 | 23:38 | +4 min | |
| Northam C.s.d. | 23:49 | 23:53 | ||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.