Detailed timetable
23:00 Orpington to Bellingham Siding
Thursday 8 October 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 75 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Orpington | 7 | 23:00 | 22:53 | -7 min | ||
| Petts Wood Junction | pass | 23:04½ | 22:56 | -8 min | ||
| Bickley Junction | pass | 23:15 | 22:59 | -16 min | ||
| Bromley South | 1 | pass | 23:16½ | 23:05 | -11 min | |
| Shortlands | 1 | pass | 23:18 | 23:10 | -8 min | |
| Ravensbourne | pass | 23:19½ | 23:10 | -9 min | ||
| Bellingham | 1 | 23:21½ | 23:28½ | 23:13 | 23:28½ | On time |
| Bellingham Siding | 23:32 | 23:32 | ||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.