Service timetable
06:05 Stockport to Warrington Central
Friday 9 October 2026
Planned service information
- Power type
- Diesel multiple unit
- Timing load / planned train type
- E
- Maximum speed
- 90 mph
- Operating characteristics
- DQ
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Stockport | 4 | 06:05 | 06:05 | On time | ||
| Glazebrook East Junction & Sidings | 06:30 | 06:40 | 06:30 | 06:40 | ||
| Birchwood | 06:44½ | 06:53 | 06:44½ | 06:53 | ||
| Warrington Central | 1 | 06:58 | 06:58 | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.