Detailed timetable
05:00 Carnforth to York
Friday 9 October 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 715
- Maximum speed
- 60 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Carnforth | 2 | 05:00 | 05:00 | On time | ||
| Bentham | 05:20 | 05:23 | 05:20 | 05:23 | On time | |
| Settle Junction | pass | 05:39 | 05:51 | +12 min | ||
| Hellifield Goods Loops | UGL | 05:45½ | 06:05½ | 06:01 | 06:01 | -4 min |
| Hellifield | pass | 06:06½ | 06:01 | -5 min | ||
| Gargrave | 1 | pass | 06:13 | 06:23 | +10 min | |
| Skipton | 2 | 06:23 | 06:26 | 06:30 | 06:35 | +9 min |
| Keighley | 1 | pass | 06:41 | 06:45 | +4 min | |
| Shipley | 1 | 06:53 | 06:54 | 06:55 | 06:56 | +2 min |
| Dockfield Junction | pass | 06:56 | 06:58 | |||
| Apperley Junction | pass | 07:02½ | 07:01 | -1 min | ||
| Armley Junction | pass | 07:08½ | 07:09 | +1 min | ||
| Whitehall Junction | pass | 07:09½ | 07:10 | +1 min | ||
| Leeds West Junction | pass | 07:10½ | 07:12 | +2 min | ||
| Leeds | 8 | 07:14 | 07:18 | 07:13 | 07:20 | +2 min |
| Neville H. West Junction | pass | 07:23 | 07:25 | +2 min | ||
| Cross Gates | 1 | pass | 07:27 | 07:28 | +1 min | |
| Micklefield | 1 | pass | 07:34 | 07:33 | -1 min | |
| Church Fenton | 4 | pass | 07:40 | 07:40 | On time | |
| Colton Junction | pass | 07:46 | 07:49 | +3 min | ||
| York | 11 | 07:55 | 07:57 | +2 min | ||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.