Service timetable
05:25 Silwood Stabling Sidings to Dalston Junction
Friday 9 October 2026
Planned service information
- Power type
- Electric multiple unit
- Timing load / planned train type
- 378
- Maximum speed
- 75 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Silwood Stabling Sidings | 05:25 | 05:18 | -7 min | |||
| New Cross Gate Dpt Hdshunt | 05:32½ | 05:37½ | 05:25½ | 05:37½ | On time | |
| New Cross Gate Dpt Wash Rd | 05:40½ | 05:49 | 05:40½ | 05:49 | ||
| Dalston Junction | 3 | 06:12 | 06:14 | +2 min | ||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.