Service timetable
10:35 Westbury Down T.c. to Goonbarrow Junction Dbc
Saturday 10 October 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 600
- Maximum speed
- 60 mph
- Operating characteristics
- Q
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Westbury Down T.c. | 10:35 | |||||
| Westbury Down Tc Ent Exit | 10:37 | 10:39 | ||||
| Tiverton Loop | 11:53½ | 12:16½ | ||||
| Exeter St Davids | 4 | 12:34½ | 12:36½ | |||
| Dawlish Warren | 1 | 12:53 | 13:03 | |||
| Plymouth | TL | 13:58½ | 14:03 | |||
| Lostwithiel Down Gds Loop | 14:52½ | 15:14 | ||||
| St Blazey Signal Box | 15:33½ | 15:36½ | ||||
| Goonbarrow Junction | 15:51½ | 15:52½ | ||||
| Goonbarrow Junction Dbc | 15:55 | |||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.