Detailed timetable
08:35 Motherwell to Glasgow Central
Sunday 11 October 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 75 mph
- Train class code
- S
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Motherwell | 3 | 08:35 | 08:34 | -1 min | ||
| Mossend South Junction | pass | 08:38 | 08:37 | |||
| Mossend West Junction | pass | 08:40 | 08:39 | |||
| Bellshill | 1 | 08:42 | 08:42 | 08:40½ | 08:42 | On time |
| Uddingston Junction | pass | 08:45 | 08:45 | |||
| Uddingston | 08:46 | 08:46 | 08:45½ | 08:46 | ||
| Newton East Junction | pass | 08:47½ | 08:47½ | |||
| Newton West Junction | pass | 08:48½ | 08:48½ | |||
| Cambuslang | 08:50 | 08:50 | 08:50 | 08:50½ | ||
| Rutherglen East Junction | pass | 08:52½ | 08:52½ | |||
| Shawfield | pass | 08:54½ | 08:54½ | |||
| Larkfield Junction | pass | 08:55½ | 08:55½ | |||
| Eglinton St Junction | pass | 08:57 | 08:57 | |||
| Glasgow Bridge Street Junction | pass | 08:59 | 08:59 | |||
| Glasgow Central | 4 | 09:01 | 09:01 | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.