17:25 London Charing Cross to Dartford
Monday 12 October 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 75 mph
- Train class code
- S
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| London Charing Cross | 3 | 17:25 | 17:24 | -1 min | ||
| London Waterloo East | A | 17:28 | 17:28 | 17:27 | 17:28 | On time |
| Ewer Street Junction | pass | 17:30 | 17:29 | -1 min | ||
| London Bridge | 7 | 17:32 | 17:34 | 17:32 | 17:34 | On time |
| Blue Anchor (Kent) | pass | 17:36 | 17:36 | On time | ||
| New Cross | pass | 17:38 | 17:38 | On time | ||
| Tanners Hill Junction (Nx) | pass | 17:39 | 17:39 | On time | ||
| Lewisham Vale Junction | pass | 17:40 | 17:40 | On time | ||
| Lewisham | 4 | 17:41 | 17:42 | 17:41 | 17:42 | On time |
| Blackheath | 2 | 17:45 | 17:45 | 17:44 | 17:45 | On time |
| Kidbrooke | 17:49 | 17:49 | 17:48 | 17:49 | On time | |
| Eltham | 17:52 | 17:53 | 17:52 | 17:53 | On time | |
| Falconwood | 17:56 | 17:56 | 17:55 | 17:55 | -1 min | |
| Welling | 17:58 | 17:59 | 17:57 | 17:58 | -1 min | |
| Bexleyheath | 18:02 | 18:02 | 18:01 | 18:02 | On time | |
| Barnehurst | 18:05 | 18:06 | 18:04 | 18:05 | -1 min | |
| Perry Street Fork Junction | pass | 18:08 | 18:07 | |||
| Crayford Creek Junction | pass | 18:09 | 18:08 | |||
| Crayford Spur A | pass | 18:10½ | 18:09½ | |||
| Dartford Junction | pass | 18:11 | 18:10 | |||
| Dartford | 1 | 18:13 | 18:12 | -1 min | ||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.