Detailed timetable
09:36 Cricklewood South Sidings to Sutton (London)
Monday 12 October 2026
Planned service information
- Power type
- Electric multiple unit
- Timing load / planned train type
- 700
- Maximum speed
- 100 mph
- Operating characteristics
- DQ
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Cricklewood South Sidings | 09:36 | 09:39 | +3 min | |||
| Cricklewood | D | 09:39½ | 09:41 | 09:42½ | 09:44 | +3 min |
| West Hampstead Thameslink | 1 | 09:43½ | 09:43½ | 09:47 | 09:47½ | +4 min |
| Carlton Road Junction | pass | 09:45½ | 09:48 | +3 min | ||
| Kentish Town | 1 | pass | 09:47 | 09:49 | +2 min | |
| Dock Junction North | pass | 09:48½ | 09:51 | +3 min | ||
| London St Pancras International LL | A | pass | 09:51½ | 09:52 | +1 min | |
| Farringdon (London) | 3 | 09:56 | 09:58 | 09:55 | 09:56 | -2 min |
| City Thameslink | 2 | pass | 09:59 | 09:57 | -2 min | |
| London Blackfriars | 1 | 10:01 | 10:03 | 10:00 | 10:01 | -2 min |
| Blackfriars Junction | pass | 10:05 | 10:02 | -3 min | ||
| Southwark Bridge Junction | pass | 10:06 | 10:03 | -3 min | ||
| Elephant & Castle | 2 | 10:07 | 10:16½ | 10:04 | 10:04 | -12 min |
| Loughborough Junction | pass | 10:21 | 10:17 | -4 min | ||
| Herne Hill | 4 | 10:25 | 10:27 | 10:21 | 10:23 | -4 min |
| Tulse Hill | 2 | 10:33½ | 10:36½ | 10:28 | 10:28 | -8 min |
| Streatham | 1 | pass | 10:39½ | 10:31 | -8 min | |
| Streatham South Junction | pass | 10:42 | 10:33 | -9 min | ||
| Mitcham Junction | pass | 10:45½ | 10:40 | -5 min | ||
| Sutton (London) | 4 | 10:53 | 10:52 | -1 min | ||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.