Service timetable
23:20 Great Malvern to Worcester Back Road
Friday 20 November 2026
Planned service information
- Power type
- Diesel multiple unit
- Timing load / planned train type
- 802
- Maximum speed
- 125 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Great Malvern | 23:20 | 23:20 | On time | |||
| Malvern Wells Loop | 23:23 | 23:32 | No report | |||
| Malvern Wells | 23:33 | 23:41 | 23:24 | 23:40 | -1 min | |
| Worcester Foregate Street | 1 | 23:52 | 23:55 | 23:50 | 23:51 | -4 min |
| Worcester Shrub Hill | 2 | 23:57½ | 00:01 | 23:57 | 23:57 | -4 min |
| Worcester Wylds Lane Junction | UM | 00:03 | 00:12 | 23:59 | 00:12 | On time |
| Worcester Back Road | 00:15 | 00:15 | ||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.