Detailed timetable

23:30 Heathrow Terminal 5 to Shenfield

Saturday 21 November 2026

Live map
Headcode: 9W58Headcode9W58 OperatorElizabeth line UIDC38058

Planned service information

Power type
Electric multiple unit
Timing load / planned train type
345
Maximum speed
90 mph
Train class code
S
Operating characteristics
D
LocationPlatformScheduledActual
ArrivalDepartureArrivalDepartureDelay
Heathrow Terminal 5423:30 23:30 On time
Heathrow Terminals 1-3223:3623:36 23:35 23:36 On time
Heathrow Tunnel Junctionpass23:39 23:39 On time
Stockley Junctionpass23:39½ No report
Heathrow Airport Junctionpass23:40 23:41 +1 min
Hayes & Harlington423:4223:42 23:41 23:42 On time
Southall423:4523:45 23:45 23:46 +1 min
Hanwell323:4823:48 23:49 23:50 +2 min
West Ealing423:5023:50 23:51 23:52 +2 min
Ealing Broadway423:5223:52 23:54 23:54 +2 min
Acton Westpass23:53½ 23:55 +2 min
Acton Main LineURL23:5523:55 23:57 23:57 +2 min
Ladbroke Grovepass23:59 No report
Portobello Junction (London)pass00:01 No report
Westbourne Park CsApass00:01½ No report
Paddington CrossrailA00:0300:07 No report
Bond StreetA00:1000:10 No report
Tottenham Court RoadA00:1200:12 00:13½ 00:13 +1 min
Farringdon CrossrailA00:1500:15 00:14 00:16 +1 min
Liverpool St CrossrailA00:1800:18 00:17 00:18 On time
Whitechapel CrossrailA00:2000:20 00:20 00:21 +1 min
Stepney Green Junctionpass00:22 00:22 On time
Pudding Mill Lane Portalpass00:26 00:24 -2 min
Stratford (London)800:2800:28 00:27 00:28 On time
Maryland200:3000:30 00:30 00:31 +1 min
Forest Gate200:3200:32 00:33 00:33 +1 min
Forest Gate Junctionpass00:33½ 00:34 +1 min
Manor Park00:3500:35 00:35 00:36 +1 min
Ilford400:3700:37 00:38 00:39 +2 min
Seven Kings400:4000:40 00:41 00:42 +2 min
Goodmayes400:4200:42 00:43 00:44 +2 min
Chadwell Heath400:4400:44 00:45 00:46 +2 min
Romford500:4700:47 00:49 00:50 +3 min
Gidea Park400:5000:50 00:52 00:53 +3 min
Harold Wood400:5300:53 00:55 00:56 +3 min
Brentwood400:5700:57 00:59 01:00 +3 min
Shenfield601:02 01:05 +4 min

Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.