Detailed timetable
09:29 Upminster L.t. to Upminster L.t.
Saturday 21 November 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 45 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Upminster L.t. | 09:29 | No report | ||||
| Turnham Green Lt | 10:44 | 10:44 | No report | |||
| Gunnersbury | 1 | 10:48 | 10:48 | 10:50 | 10:50 | +2 min |
| Kew Gardens | 2 | 10:50 | 10:50 | 10:53 | 10:53 | +3 min |
| Richmond NLL | 7 | 10:55 | 11:05 | 10:58 | 11:04 | -1 min |
| Kew Gardens | 1 | 11:09 | 11:09 | 11:08 | 11:08 | -1 min |
| Gunnersbury | 2 | 11:12 | 11:12 | 11:12 | 11:12 | On time |
| Turnham Green Lt | 11:15 | 11:15 | 11:14½ | 11:15 | On time | |
| Upminster L.t. | 12:29 | 12:28½ | ||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.