Detailed timetable
07:05 Stone to Bescot Up Engineers Sidings
Sunday 22 November 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 1400
- Maximum speed
- 60 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Stone | 07:05 | 07:05 | On time | |||
| Colwich | 07:17 | 08:55½ | 07:13 | 07:13 | -102 min | |
| Rugeley North Junction | pass | 09:01½ | 07:18 | -103 min | ||
| Rugeley Trent Valley | 1 | pass | 09:03 | 08:46 | -17 min | |
| Rugeley Power Station Junction | pass | 09:04½ | 08:47 | -17 min | ||
| Rugeley Town | pass | 09:06 | 08:48 | -18 min | ||
| Hednesford | pass | 09:21 | 08:55 | -26 min | ||
| Mid Cannock Junction | pass | 09:27½ | No report | |||
| Bloxwich | pass | 09:36½ | 09:05 | -31 min | ||
| Ryecroft Junction | pass | 09:41½ | 09:09 | -32 min | ||
| Walsall | UFL | pass | 09:43½ | 09:12 | -31 min | |
| Pleck Junction | pass | 09:46 | 09:13 | -33 min | ||
| Bescot Stadium | pass | 09:50 | 09:16 | -34 min | ||
| Bescot Up Engineers Sidings | 09:53½ | 09:19 | -34 min | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.