Service timetable
09:06 Eastleigh East Yard to Petersfield
Sunday 22 November 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 400
- Maximum speed
- 60 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Eastleigh East Yard | 09:06 | 08:51 | -15 min | |||
| Farnborough (Main) | 1 | 09:49½ | 09:54½ | 09:47 | 09:47 | -7 min |
| Woking Up Yard Entry/Exit | 10:15 | 11:12 | No report | |||
| Woking | 1 | 11:13 | 11:18 | 11:13 | 11:18 | On time |
| Guildford | 4 | 11:30 | 11:32 | 11:29 | 11:29 | -3 min |
| Petersfield | 2 | 12:03 | 12:02 | -1 min | ||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.