Detailed timetable
00:01 Dalston Junction to New Cross Gate C.s.d
Sunday 22 November 2026
Planned service information
- Power type
- Electric multiple unit
- Timing load / planned train type
- 378
- Maximum speed
- 75 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Dalston Junction | 2 | 00:01 | 00:03 | +2 min | ||
| Haggerston | 2 | pass | 00:02½ | No report | ||
| Shadwell | 2 | pass | 00:12 | No report | ||
| Canada Water | 3 | pass | 00:17½ | 00:14 | -3 min | |
| Surrey Quays Silwood Junction | pass | 00:20 | No report | |||
| Canal Junction (New Cross) | pass | 00:22 | 00:22 | On time | ||
| New Cross Gate C.s.d | 00:24 | 00:24 | On time | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.